An order though that. Excuse me. That you've now extended four times over the last year, keeping this plan open between May and December. According to figures we have Last year [the J.H. Campbell coal plant] cost more than $135 million. And with each extension of this order, obviously that price tag will continue to go up. So as you can imagine, the question of who's actually footing this bill is of serious concern to my constituents in Michigan. (00:11–00:44)
CLAIM
Asserts that the operation of the coal plant cost over $135 million last year.
This is an excerpt from a raw transcript. The assertions have not been audited or verified. Tap the video to view the source footage and understand the context.